Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

You are currently working on a project to be completed in 20 months. The budget of the project is R12 000 000. Six months have

You are currently working on a project to be completed in 20 months. The budget of the project is R12 000 000. Six months have passed, and the schedule says that 30% of the work should be completed. To date R2 800 000 has been spent already, however on a closer review; you find that only 15% of work has been completed.

4.1.Calculate the projects Planned Value (PV). (5 Marks)

4.2.Calculate the projects Earned Value (EV). (5 Marks)

4.3.Calculate the projects Cost Variance (CV) and determine if the project is under budget or over budget. (5 Marks)

4.4.Calculate the projects Schedule Variance (SV) and determine if the project is behind schedule or ahead of schedule.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Modeling An Introductory Guide To Excel And VBA Applications In Finance

Authors: Joachim Häcker, Dietmar Ernst

1st Edition

1137426578, 978-1137426574

More Books

Students also viewed these Finance questions

Question

T F The face value for most corporate bonds is $5,000.

Answered: 1 week ago