You are developing a performance progress report for a project you are managing. The following timephased budget was developed earlier in the planning stage and

You are developing a performance progress report for a project you are managing. The following timephased budget was developed earlier in the planning stage and is being used as the standard against which the project performance is measured.
\table[[Activities,W1,W2,W3,W4,W5,W6,W7,W8,W9,W10,W11],[A,2,3,1,,,,,,,,],[B,,,,5,8,6,,,,,],[C,,,,,,,4,6,1,7,4],[Total,2,3,1,5,8,6,4,6,1,7,4]]
At the end of Week 6, Activity "B" is 90% complete and its actual cost is 15. What is the Planned Value of this activity?
Use two decimal places in your calculations.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction To Emergency Management

Authors: Jane A Bullock, George D Haddow

7th Edition

0128171391, 9780128171394

More Books

Students also viewed these General Management questions

Question

3. Avoid making mistakes when reaching our goals

Answered: 1 week ago