Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

You are developing a performance progress report for a project you are managing. The following timephased budget was developed earlier in the planning stage and

You are developing a performance progress report for a project you are managing. The following timephased budget was developed earlier in the planning stage and is being used as the standard against which the project performance is measured.
\table[[Work Packages,W1,W2,W3,W4,W5,W6],[A,4,8,6,,,],[B,,,,6,,],[C,,,,,7,8],[Total,4,8,6,6,7,8]]
You are analyzing the project performance at the end of Week 5. Activity "C" is 80% complete and its actual cost is 15. What is the schedule variance of this activity?
Use two decimal places in your calculations.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Wildlife Ecology Conservation And Management

Authors: Anthony R. E. Sinclair, John M. Fryxell, Graeme Caughley

2nd Edition

1405107375, 978-1405107372

More Books

Students also viewed these General Management questions

Question

L A -r- P[N]

Answered: 1 week ago

Question

What is the main advantage to this tactic?

Answered: 1 week ago

Question

What administrative cost items are associated with this tactic?

Answered: 1 week ago

Question

What is the full-cost budget?

Answered: 1 week ago