You are doing a process improvement project in a widget manufacturing company. You determine that you must produce 800 widgets weekly for the customer. Your
You are doing a process improvement project in a widget manufacturing company. You determine that you must produce 800 widgets weekly for the customer. Your organization has a standard 40-hour workweek. Additionally, you must conduct quality checks every 2 hours. What is your Takt time? A.3.4 B.3 C.3.1 D.5