You are evaluating the following project. All $ are in millions Initial cost of the project at t=0 is $70. Annual cash flows from the

You are evaluating the following project. All $ are in millions Initial cost of the project at t=0 is $70. Annual cash flows from the project depends on the demand for the product and is estimated to be as follows: With probability of 30%, the demand is high and the annual cash flow is $45 With probability of 40%, the demand is average and the annual cash flow is $30 With probability of 30%, the demand is low and the annual cash flow is $15 The above cash flows occur for the next 3 years, that is, until from t=1 to t=3. The company plans to finance the project by issuing bonds and stocks. The company will issue a ten-year bond at par with the coupon rate of 5%. The companys stock has a beta of 2.1. The risk-free rate is 2.07% and the market risk premium is 6%. The marginal tax rate of the firm is 40%. The firms target and current capital structure is 40% debt and 60% equity. Questions: (In your calculations, please keep up to two decimal points after %. For example, 12.34%.)

1. What is the expected NPV of the project?

2. What feature of the project makes the managers hesitant with starting this project?

3. Now assume that if we wait one year, we will gain additional information regarding demand. That is, at t=1, we will know whether the demand will be high, average, or low. (The probability of the demand is 30%,40%,30% at t=0 and then becomes certain at t=1). Find out the expected NPV of the project. The same demand continues throughout the life of the project. (That is, the demand is high-high-high with 30%, avg-avg-avg with 40%, and low-low-low with 30%). The demand cannot be, for example, high-low-avg.

In Q3, the following paragraph provides further information. 3. Now assume that if we wait one year, we will gain additional information regarding demand and can decide whether to do the project or not at t=1. That is, at t=1, we will know whether the demand for the product will be high, average, or low. (The probability of the demand is 30%,40%,30% at t=0 and then becomes certain at t=1). If you decide to do the project at t=1, the initial cost occurs at t=1, and cash flow according to the demand type will stay the same during the life of the project until t=4. Find out the expected NPV of the project at t=0.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Liars Poker Rising Through The Wreckage On Wall Street

Authors: Michael Lewis

1st Edition

0393246108,0393247147

More Books

Students also viewed these Finance questions

Question

Which customer did the company sell the most to in November?

Answered: 1 week ago

Question

What is the combined tax rate for Alabama (AL)?

Answered: 1 week ago