Question

1 Approved Answer

You are evaluating the following two projects: ( Click on the following icon in order to copy its contents into a spreadsheet. ) Year -

You are evaluating the following two projects:(Click on the following icon in order to copy its contents into a spreadsheet.)
Year-End Cash Flows($ thousands)
Project
0
1
2
X
negative 30
20
20
Y
negative 80
40
60
Use the incremental IRR to determine the range of discount rates for which each project is optimal to undertake. Note that you should also include the range in which it does not make sense to take either project.
Question content area bottom
Part 1
Fill in the incremental cash flows in the bottom row of the chart:(Round to the nearest integer.)
Year-End Cash Flows($ thousands)
Project
0
1
2
X
negative 30
20
20
Y
negative 80
40
60
Incremental Cash Flow
enter your response here
enter your response here
enter your response here
Part 2
Find the incremental IRR and the IRR for the projects. Fill in the IRR for Project X, Project Y, and the incremental IRR:(Round to two decimal places.)
Year-End Cash Flows($ thousands)
Project
0
1
2
IRR
X
negative 30
20
20
enter your response here%
Y
negative 80
40
60
enter your response here%
Upper Y minus Upper X
negative 50
20
40
enter your response here%
Part 3
Use the incremental IRR rule to decide between the two projects. (Select from the drop-down menus and round to two decimal places.)
Project
X
Y
should be taken on for discount rates below
enter your response here% and Project
X
Y
should be taken on for discount rates above
enter your response here%. Neither project should be taken on for discount rates above
enter your response here%.
Note that you should also include the range in which it does not make sense to take either project.Note that you should also include the range in which it does not make sense to take either project.Note that you should also include the range in which it does not make sense to take either project.)))Projectshould be taken on for discount rates belowshould be taken on for discount rates below% and Project% and Projectshould be taken on for discount rates aboveshould be taken on for discount rates above%.Neither project should be taken on for discount rates above%.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Analysis Of Financial Data

Authors: Gary Koop

1st Edition

0470013214, 978-0470013212

More Books

Students also viewed these Finance questions