You are given the following information: Quantitative Risk Assessment. Assume the following information for an IT project. Consequences of Failure Cost =.9 Schedule =.7 Performance
You are given the following information: Quantitative Risk Assessment. Assume the following information for an IT project. Consequences of Failure Cost =.9 Schedule =.7 Performance =.3 Future Business =.5 Probability of Failure Maturity of Failure =.7 Complexity =.7 Dependency =.5 Client Concerns =.5 Programmer Skill =.3 Calculate the overall risk factor for this project. Would you assess this level of risk as low, moderate, or high