You are given the following network. Activity Immediate Predecessors Normal Completion Time (Weeks) Crash Completion Time (Weeks) Normal Cost (Total) Crash Cost (Total) A --
You are given the following network.
Activity | Immediate Predecessors | Normal Completion Time (Weeks) | Crash Completion Time (Weeks) | Normal Cost (Total) | Crash Cost (Total) |
A | -- | 6 | 6 | $100 | $100 |
B | A | 10 | 4 | $2,000 | $2,600 |
C | A | 10 | 8 | $800 | $920 |
D | B | 6 | 5 | $700 | $750 |
E | B | 8 | 6 | $1,000 | $1,140 |
F | C,D | 9 | 7 | $1,400 | $1,550 |
G | E | 14 | 10 | $3,000 | $3,320 |
H | E,F | 10 | 8 | $900 | $1,020 |
e) Now, for every week that the project is reduced, there is a $120 benefit. What is the minimum
cost schedule and what is the cost of the project considering the benefit received. Also identify which activities to crash and by how many weeks.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started