You are in the process of developing the project management plan, and the project sponsor has provided additionall requirements. What should you do first? Update
You are in the process of developing the project management plan, and the project sponsor has provided additionall requirements. What should you do first?
Update the project management plan.
Request a change to the project scope.
C Analyze the impact of the additional requirements on the project.
D
Implement the additional requirements immediately.