You are managing a constructions project. You have completed half the project work. The total planned cost at this stage is $10000. The actual work
You are managing a constructions project. You have completed half the project work. The total planned cost at this stage is $10000. The actual work that has been completed at this stage is worth $6200. You have spent $6500 already on the project. What is the CPI?