You are managing a few projects and the sponsor asks you to submit CPI and TCPI numbers for them. You provided CPI = 1 for project A, CPI = 1.2 for project B, TCPI = 0.9 for project C and TCPI = 1.2 for project D. Which project do you think the sponsor might terminate based on this data