You are managing a project with an estimated budget at completion of $ 5 0 0 , 0 0 0 . According to the schedule,

You are managing a project with an estimated budget at completion of $500,000. According to the schedule, your team should have completed 40% of the work by now. The most recent calculations show the work is 35% done and the project has cost $225,000 so far. Your sponsor asks you about the status of the project. What should you tell them?
You are managing a project with an estimated budget at completion of $500,000. According to the schedule, your team should have completed 40% of the work by now. The most recent calculations show the work is 35% done and the project has cost $225,000 so far. Your sponsor asks you about the status of the project. What should you tell them?
The project is behind schedule and over budget
The project is ahead of schedule and over budget
The project is under control
The project is behind schedule and under budget
The project is ahead of schedule and under budget

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Rethinking Prestige Branding: Secrets Of The Ueber-Brands

Authors: Wolfgang Schaefer, J P Kuehlwein

1st Edition

0749470038, 9780749470036

More Books

Students also viewed these General Management questions