Question: You are performing stakeholder analysis for an upcoming project. You have decided to use the Salience Model. Which factors will you analyze? A ) Power

You are performing stakeholder analysis for an upcoming project. You have decided to use the Salience Model. Which factors will you analyze?
A) Power and Influence
B) Power, urgency, and legitimacy
C) Power and Interest
D) Influence and Impact