You are planning your project and reviewing resource optimization tools and techniques. You want to clearly identify certain tasks as milestones. How do you set

You are planning your project and reviewing resource optimization tools and techniques. You want to clearly identify certain tasks as milestones. How do you set a milestone in MS Project

A) MS Project will automatically identify the milestones for the project.

B) Right click and set the milestone attribute

C) Set the duration to zero time units.

D) Set the effort for the task to zero time units.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Hands-On Database

Authors: Steve Conger

2nd Edition

0133024415, 978-0133024418

More Books

Students also viewed these Databases questions