Question

1 Approved Answer

You are sourcing an assembly component ( item number: C 1 2 1 0 ) from two suppliers: Supplier A and B . During the

You are sourcing an assembly component (item number: C1210) from two suppliers: Supplier A and B.
During the previous year, Supplier A delivered components worth $500,000, and there were 10 instances of late delivery and 200 defective items that required rework. Supplier B delivered components worth $200,000, with 100 defective items requiring rework and one occurrence necessitating the return of the entire shipment to the supplier.
The average cost for each type of failure event is as follows:
- Late delivery: $2,000(per occurrence)
- Rework: $50(per item)
- Return to supplier: $10,000(per occurrence)
Below is the unit component price from each supplier:
- Supplier A: $510(per component)
- Supplier B: $505(per component)
What is the Supplier Performance Index (SPI) of Supplier A?(round to two-digit if needed)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Information Technology Project Management

Authors: Kathy Schwalbe

6th Edition

978-111122175, 1133172393, 9780324786927, 1111221758, 9781133172390, 324786921, 978-1133153726

More Books

Students also viewed these General Management questions

Question

Evaluate: int sin^{2}x~cos^{4}xdx

Answered: 1 week ago

Question

Explain about sorting in Detail? with examples

Answered: 1 week ago

Question

Find the arc length of the curve y=3x^{12}-1 from x=0 to x=1.

Answered: 1 week ago