Question

1 Approved Answer

You are sourcing an assembly component (item number: KN95) from two suppliers: Supplier X and Y. In the last year, Supplier X delivered $200,000 worth

You are sourcing an assembly component (item number: KN95) from two suppliers: Supplier X and Y.

In the last year, Supplier X delivered $200,000 worth of the components, and there were 12 instances of late delivery. Supplier Y delivered $100,000 worth of the components, and there were in total 200 defective items that had to be reworked.

The average cost for each type of failure event is as follows:

- Late delivery: $2,000 (per occurrence)

- Rework: $50 (per item)

Below is the unit component price from each supplier:

- Supplier X: $500 (per component)

- Supplier Y: $510 (per component)

Which supplier had the lower total cost in the last year?

a. Supplier X

b. Supplier Y

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamental accounting principle

Authors: John J. Wild, Ken W. Shaw, Barbara Chiappetta

21st edition

1259119831, 9781259311703, 978-1259119835, 1259311708, 978-0078025587

Students also viewed these Finance questions