You are the financial manager of the Crossrail 1 project in London. The Board overseeing the project, acting on behalf of the UK Government, has

You are the financial manager of the Crossrail 1 project in London. The Board overseeing the project, acting on behalf of the UK Government, has asked you to provide a financial analysis of the project for business planning purposes. With two years to go before the commencement of train operations, you have assembled the most recent estimates of the capital investment cost and net revenues, which were forecast 1 year ago. While the user benefits and ticket revenues are assumed to remain the same each year of the 60-year useful life, it is anticipated that maintenance costs will be higher in the final 30 years of the project. They are shown in Table 1.

Item of cash flow Today (bn) Each year (for the first 30 years) (bn) Each year (for years 31 to 60) (bn)
Capital investment -9.4
User benefits (Includes Time savings, Traffic congestion relief) 0.843 0.843
Ticket revenues 0.3 0.3
Operational costs and maintenance -0.422 -0.609

For projects such as Crossrail 1, the UK Government typically estimates a 60-year useful life and uses a discount rate of 3.5%.

a) What is the net present value (NPV) of the project? [ Select ] ["15.04", "8.83", "7.36", "16.76"]

b) What is the payback period of the project? [ Select ] ["13.04", "8.22", "17.60", "7.49"]

c) What is the internal rate of return (IRR) of the project? [ Select ] ["7.57%", "7.35%", "5.44%", "6.52%"]

d) Based on your calculations is Crossrail 1 a viable project at the discount rate? [ Select ] ["Yes", "No"]

You have been asked by the Board to present an analysis that incorporates more recent cash flow information about the Crossrail 1 project. Before the project becomes operational, the capital investment has been given a worse scenario estimate that is 35% above the forecast in table 1. The Board would like to see the analysis if the net cash inflows will also be 35% below expectation over the 60-year life whether under the existing hurdle rate of 3.5% it would remain viable.

a) What is the net present value (NPV) of the project? [ Select ] ["-2.16", "4.78", "3.20", "-1.80"]

b) What is the internal rate of return (IRR) of the project? [ Select ] ["2.72%", "3.10%", "1.79%", "0.67%"]

c) Based on your calculations is Crossrail 1 a viable project at the discount rate? [ Select ] ["Yes", "No"]

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Amazon Fba E Commerce Business Model In 2020 $10 000

Authors: Roberts Ronald

1st Edition

1951595777, 978-1951595777

More Books

Students also viewed these Finance questions

Question

Discuss the interrelatedness of the four management functions.

Answered: 1 week ago