you are the manager in the production department in a solar panel manufacturing company. One of your primary goals for the most recent month was
you are the manager in the production department in a solar panel manufacturing company. One of your primary goals for the most recent month was to control costs. Your department manufactures 500 solar panels per month, and your direct labour hours were 920 hours for the month, paid at $30 per hour. Standards indicate that each solar panel would use two direct labour hours, paid at $25 per hour.