Question

1 Approved Answer

You are the manager of a project to improve a billing process at your firm. The table below contains the data you will need to

You are the manager of a project to improve a billing process at your firm. The table below contains the data you will need to conduct a cost analysis of the project. Indirect costs are $1,800 per week, and penalty costs are $800 per week after week 12.

Activity,Immediate Predecessor(s),Normal Time (weeks),Crash Time (weeks),Normal Cost ($),Crash Cost ($) A,-,4,1,"5,500","7,500" B,-,5,3,"8,500","9,500" C,A,1,1,"3,500","3,500" D,B,6,3,"6,000","11,500" E,"B, C",7,6,"4,500","7,000" F,D,7,6,"3,500","6,500"

a. What is the minimum-cost schedule for this project?

The minimum-cost schedule is weeks. (Enter your response as an integer.)

b. What is the difference in total project costs between the earliest completion time of the project using "normal" times and the minimum-cost schedule you derived in part (a)?

The minimum-cost schedule costs $ ??? less than using the "normal" times. (Enter your response as an integer.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Lean Six Sigma For Supply Chain Management

Authors: James Martin

1st Edition

0071735585, 9780071735582

More Books

Students also viewed these General Management questions