You are the PM on a project, and you need to decide which vendor to choose as a supplier for one of the components of

  1. You are the PM on a project, and you need to decide which vendor to choose as a supplier for one of the components of a product. Vendor A has offered the component to you at $50,000 up front with a recurring cost of $5,000 per year. Vendor B would charge you $70,000 as the initial fee then a $2,000 cost per year.

  1. What is the point in years which the costs will be equal? (3 points)

b.If the project is supposed to last 5 years, which vendor should you choose? (3 points)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Investments An Introduction

Authors: Herbert B Mayo

9th Edition

324561385, 978-0324561388

More Books

Students also viewed these Finance questions

Question

what is a peer Group? Importance?

Answered: 1 week ago

Question

Are there any KPIs that would be appropriate here?

Answered: 1 week ago

Question

Which orders were created after shipment?

Answered: 1 week ago