You are the project manager for a health management ERP project at a healthcare facility. You are trying to figure out the costs of some
You are the project manager for a health management ERP project at a healthcare facility. You are trying to figure out the costs of some resources. You decided to ask the procurement department at the hospital. Which cost estimation method are you using by doing so? A. Expert judgment B. Parametric estimating C. Bottom-up estimating D. Analogous estimating