You are the project manager of the HUB Project and your team is in its third sprint. The project aims to build an application that

You are the project manager of the HUB Project and your team is in its third sprint. The project aims to build an application that will help home construction planners computer the cost of goods, labor, permits, and provide ordering of materials from their preferred vendors based on cost estimates. The team has been completing eight story points in each of its last sprints. The backlog has a total of 102 story points remaining. Assume these are 2 week sprints.

1. What is the velocity for this team?

2. How long will it take the team to complete the project based on its current velocity?

3. The product owner is interested in a priority which is currently ranked 79 out of the 102 requirements. Based on the velocity of the team what's the lead time of this requirement?

4. How is lead time different than cycle time?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Tourism Concepts And Practices

Authors: John R Walker, Josielyn T Walker

1st Edition

0138142459, 9780138142452

More Books

Students also viewed these General Management questions

Question

y = a r c s i n ( 2 x )

Answered: 1 week ago

Question

Speak clearly and distinctly with moderate energy

Answered: 1 week ago

Question

Get married, do not wait for me

Answered: 1 week ago