You are the Project Manager to install a new baseball field in a Boston, NY suburb. All funding has been generated and the city is
You are the Project Manager to install a new baseball field in a Boston, NY suburb. All funding has been generated and the city is requesting you to develop a project network plan needed in order to provide the final project approval. You have already gathered the task estimates and the dependencies from all the subject matter experts (SMEs) as shown below. Show your project network with the activity early, late and slack times. Note the critical path and determine the number of days it will take to complete the new fields. All work must be shown.
Task ID | Description | Predecessor | # of Days |
A | Stake layout of fields and buildings | n/a | 5 |
B | Final Design Approval | A | 20 |
C | Order and delivery of building and landscape materials | A | 30 |
D | Build bathrooms and Locker Rooms | B,C | 40 |
E | Build Concession Stands | B,C | 45 |
F | Install parking lot | D,E | 15 |
G | Install lighting | F | 30 |
H | Complete Landscaping | G | 25 |
I | Hire and train staff | E | 15 |
J | Stock concession stands and bathrooms/locker rooms | E, D | 10 |
K | Final approval and Grand Opening | J | 5 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started