You are the subcontractor on a large office renovation project responsible for installing energy efficient windows. The project baselines defines that the project will be
You are the subcontractor on a large office renovation project responsible for installing energy efficient windows. The project baselines defines that the project will be completed in months with a total cost of the installation of $ After months, fifty percent of the work has been completed and $ has been spent. What is the variance at completion?
A: $
B: $
C: $
D: $