You are working on a project having following details. Activity Predecessor Duration(days) Resource A - 2 Ali@Rs100/hour B A 2 Ali@Rs100/hour C B 2 Ali@Rs100/hour
You are working on a project having following details.
Activity | Predecessor | Duration(days) | Resource |
A | - | 2 | Ali@Rs100/hour |
B | A | 2 | Ali@Rs100/hour |
C | B | 2 | Ali@Rs100/hour |
At the end of day 6 you get the following field report.
Activity | Actual % Complete | Incurred Cost in Rupees |
A | 100 | 2400 |
B | 50 | 3400 |
C | 0 | 0 |
Using earned value analysis fill the following table.
Activity | BCWS | BCWP | ACWP | SV | CV | EAC | BAC |
A |
|
|
|
|
|
|
|
B |
|
|
|
|
|
|
|
C |
|
|
|
|
|
|
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started