Question

1 Approved Answer

You are working with the Pennsylvania office to lease a building in a new office park to accommodate the expansion of the companys workforce. You

You are working with the Pennsylvania office to lease a building in a new office park to accommodate the expansion of the companys workforce. You are almost done with the Organizing Phase of the project and are just putting the cost baseline together. You have worked with the architecture firm and the general contractor to develop a detailed cost estimate for the Design Phase. The architecture bottom-up costs are presented here.

Labour

Labour Hours

Labour Rates per Hour

Sr. Architect

350

$225

Jr. Architect

1200

$165

Administrative

500

$55

Project Manager

300

$125

General Contractor

100

$115

Physical Resources

Amount

Rate

Equipment

0

Material

0

Supplies

$13,100

Locations

0

Other Costs

Amount

Direct Costs

Travel (mileage)

1,000

$0.55

Permits

5

$4, 520

Indirect Costs

Overhead

2% of All costs excluding Contingency Costs.

Contingency

5% of $818, 040

What is the Bottom-up Estimate?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions