You are working with the Pennsylvania office to lease a building in a new office park to accommodate the expansion of the companys workforce. You
You are working with the Pennsylvania office to lease a building in a new office park to accommodate the expansion of the companys workforce. You are almost done with the Organizing Phase of the project and are just putting the cost baseline together. You have worked with the architecture firm and the general contractor to develop a detailed cost estimate for the Design Phase. The architecture bottom-up costs are presented here.
Labour | Labour Hours | Labour Rates per Hour |
Sr. Architect | 350 | $225 |
Jr. Architect | 1200 | $165 |
Administrative | 500 | $55 |
Project Manager | 300 | $125 |
General Contractor | 100 | $115 |
Physical Resources | Amount | Rate |
Equipment | 0 |
|
Material | 0 |
|
Supplies |
| $13,100 |
Locations | 0 |
|
Other Costs | Amount |
|
Direct Costs |
|
|
Travel (mileage) | 1,000 | $0.55 |
Permits | 5 | $4, 520 |
Indirect Costs |
|
|
Overhead |
| 2% of All costs excluding Contingency Costs. |
Contingency |
| 5% of $818, 040 |
What is the Bottom-up Estimate?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started