Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

You have a budgeted cost of a project at $200,000 evenly spread over the projects 1 year expected completion timeframe including the tasks. After 9

You have a budgeted cost of a project at $200,000 evenly spread over the projects 1 year expected completion timeframe including the tasks. After 9 months (3 quarters), you have completed 80 percent of the project tasks at a total cost of $150,000. I have to complete a chart, its down below.

image text in transcribed

References Mailings Review View Zotero Help Aav A BE AT cD AEB 1 Normal 1 No Spac... Heading 1 Heading 2 Heading 3 Title Paragraph Styles Propiem. You have a budgeted cost of a project at $200,000 evenly spread over the project's 1 year expected completion timeframe including the tasks. After 9 months (3 quarters), you have completed 80 percent of the project tasks at a total cost of $150,000 Complete the following table as appropriate. Hint: Not all cells will need to be completed. Qtr Planned Value (PV) Actual | Earned Cost (AC)Value (EV) SPI EAC ETC Total *Formulas: EAC = BAC / CPI EAC = AC + ETC SV = EV - PV CV = EV - AC CPI = EV / AC SPI = EV / PV 1. What is the project's BAC? 2. In reference to the schedule, you are a) Ahead of schedule, b) Behind schedule, c) On schedule, or d) Cannot be determined P Parker Spring 2020 2 O EL 2 - 9 N o o " - w

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing Investments

Authors: Barbara Davison

1st Edition

0894134272, 978-0894134272

More Books

Students also viewed these Accounting questions

Question

3. Identify and describe nine cultural value orientations.

Answered: 1 week ago

Question

d. How were you expected to contribute to family life?

Answered: 1 week ago