You have a fixed-work task in Microsoft Project. The task has 2 full time resource available for 8 hours each day, and it has a
You have a fixed-work task in Microsoft Project. The task has 2 full time resource available for 8 hours each day, and it has a 5-day duration with 80 hours of work. What happens to the project in terms of resource unit, work or duration in the following scenario? 1. If 1 full-time resource quit the project and you are unable to get a replacement. 2. If you find out that you have 4 days to complete the task rather than 5 3. If you find out that the task will take 10 hours of additional work.