Question
1 Approved Answer
You have a project to build a new fence. The fence is four sided as shown below. Each side is to take one day to
You have a project to build a new fence. The fence is four sided as shown below. Each side is to take one day to build and is budgeted for $1,000 per side. The sides are planned to be completed one after the other. Today is the end of day three. (Assume that the sides have a FINISH-TO-FINISH relationship)
Using the project status chart below, fill in the blanks in the chart (Use "PV" as an example) - All calculations to be done to 3 decimal places.
Activity | Day 1 | Day 2 | Day 3 | Day 4 | Status End of Day 3 |
Side 1 | S ---------- F | Complete, spent $1,000 | |||
Side 2 | S ----F----PF | Complete, spent $900 | |||
Side 3 | S---- | PS-------PF | 50% done, spent $1000 | ||
Side 4 | S----- | PS-------PF | 75% done, spent $400 |
Key: S = Actual Start
F = Actual Finish
PS = Planned Start
PF = Planned Finish
What Is: | Calculation | Answer | Interpretation of the Answer | |
PV | 1000 + 10000 + 10000 | 3000 | We should have done $3000 worth of work | |
EV | ||||
AC | ||||
BAC | ||||
CV | ||||
CPI | ||||
SV | ||||
SPI | ||||
EAC | ||||
ETC | ||||
VAC | ||||
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started