You have a project with an SPI of 0.85 and a CPI of 1.1. What is the status of the project? Question 7 options: Ahead
You have a project with an SPI of 0.85 and a CPI of 1.1. What is the status of the project? Question 7 options: Ahead of schedule and under budget. Behind schedule and over budget. Ahead of schedule and over budget. Behind schedule and under budget