Question
You have acquired a revolutionary piece of software from inner Australia, which you are going to install as soon as possible for a client. You
You have acquired a revolutionary piece of software from inner Australia, which you are going to install as soon as possible for a client. You have contracted to have the system installed and users trained in 17 days, paying a penalty of $300 per day beyond 17 days. The critical path data for the project is:
Activity | Duration | Predecessor |
A get import license | 10 days | None |
B shipping | 8 days * | A |
C train users in method | 16 days | None |
D train on system | 2 days | B,C |
You have options (*) for shipping (activity B):
Slow boat | 8 days | $100 |
Fast boat | 7 days | $200 |
Bush airplane | 5 days | $400 |
Normal airplane | 3 days | $600 |
Chartered plane | 1 day | $900 |
Conduct a crashing analysis to determine the economically optimal choice of delivery.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started