You have an hour to complete this activity. Project Lovelife Team has started gathering information necessary to develop a project network - predecessor activities and
You have an hour to complete this activity.
Project Lovelife Team has started gathering information necessary to develop a project network - predecessor activities and activity time in days. The results of their meeting are found below:
7
- Activity 1 is Project Lovelife (1 point)
- Project Start date is January 2, 2008. (1 point)
- Plot the following holidays: (All 5 holidays were plotted correctly; minus 0.50 pts for every holiday not plotted)
- New Year's Day - Jan 1, 2008
- Family Day - Feb 20, 2008
- Company Holiday - Mar 28, 2008
- Victoria Day - May 19, 2008
- Canada Day - Jul 1, 2008
- Make sure each activity is showing WBS code (outline number) (1 point)
- Critical task should be highlighted (1 point)
- Column showing slack days per activity (1 point)
- Gantt chart showing 'entire project view' (1 point)
Answer the following with references and MS Project (5 points each):
- What is the exact project duration and date of completion? 98 days 2008- may 22
- What activities lie on the critical path? Indicate the WBS code and Description.1.9 and 1.2
- How sensitive is the network?
- Identify two sensible milestones and explain your choices.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started