You have been asked to balance a flow shop assembly operation to achieve an output rate of 80 units over two eight-hour shifts - 16

You have been asked to balance a flow shop assembly operation to achieve an output rate of 80 units over two eight-hour shifts - 16 hours. Task times and precedence relationships are shown in the table below:

Task Predecessor Time(minutes)
A -- 2
B A 4
C 7
D A,B 11
E C 9
F D 10
G E,F 7
H D,G 4

a. What is the cycle time in Minutes?

b. What is the theoretical number of stations?

c. Based on Longest Operating Time, were you able to group based on the theoretical number of stations?

d. What is station E assigned to?

e. Based on your grouping and following the longest operating time rule, is there and opportunity to balance the line more efficiently? If so, what is the new cycle time?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Contemporary Strategy Analysis Text and Cases

Authors: Robert M. Grant

9th edition

978-1119120841, 1119120845, 978-1119120834

More Books

Students also viewed these General Management questions

Question

=+At what price should it plan to sell the product?

Answered: 1 week ago