Question
You have been asked to balance a flow shop assembly operation to achieve an output rate of 80 units over two eight-hour shifts - 16
You have been asked to balance a flow shop assembly operation to achieve an output rate of 80 units over two eight-hour shifts - 16 hours. Task times and precedence relationships are shown in the table below:
Task | Predecessor | Time(minutes) |
A | -- | 2 |
B | A | 4 |
C | 7 | |
D | A,B | 11 |
E | C | 9 |
F | D | 10 |
G | E,F | 7 |
H | D,G | 4 |
a. What is the cycle time in Minutes?
b. What is the theoretical number of stations?
c. Based on Longest Operating Time, were you able to group based on the theoretical number of stations?
d. What is station E assigned to?
e. Based on your grouping and following the longest operating time rule, is there and opportunity to balance the line more efficiently? If so, what is the new cycle time?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started