you have been asked to evaluate a project performance using earned value management techniques. It is currently day 50.70 of a project. BCWS BCWP and
you have been asked to evaluate a project performance using earned value management techniques. It is currently day 50.70 of a project. BCWS BCWP and AC to date are 26.28m 28.37m and 33.37m respectively. Then what is the CV of the project to date