You have been asked to prepare a network diagram and identify the critical path for a project with 10 activities described in the table below.
You have been asked to prepare a network diagram and identify the critical path for a project with 10 activities described in the table below. Activity Duration (Days) Preceding Activities A 5 E B 10 F, J 3 D 2 B, G E C 3 K H H C L WJ A, H K F 13. What is the critical path for the project? a. C, H, J, B, D b. C, H, G, D C. C, E, A, B, D d. C, A, E, J, B, D e. There are multiple critical paths