You have been assigned to manage a new project for your company. The activity on node ( AON ) diagram for the project is given
You have been assigned to manage a new project for your company. The activity on node AON diagram for the project is given below:
tableActivitytableTimein weeksABCDEFGHI
What is the critical path?
The critical path is
What is the slack for activity H
Slack for activity weeks
What is the slack for activity C
Slack for activity is weeks
What is the early start ES time for activity
What is the late finish LF time for activity
If we process activity faster to finish it weeks earlier than expected, then:
The project completion time would be by weeks write in the second box if the project completion time will stay the same
An unexpected event delays activity by weeks. This means:
The project completion time would be by weeks write in the second box if the project completion time will stay the same
An unexpected event delays activity by weeks. This means:
The project completion time would be by weeks write in the second box if the project completion time will stay the same
You are considering crashing the project to complete it faster. Crashrelated information is given in the table below.
What is the total cost to crash the activities and achive the target project completion time?
Total crash cost
If you were given a bonus to reduce the project completion time by weeks what will be your decision?
Decision:
You have been assigned to manage a new project for your company. The activity on node AON diagram for the project is given below:
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started