You have been contracted to undertake a project for a firm. The project parameters are listed in the table below a) Draw the network diagram.

You have been contracted to undertake a project for a firm. The project parameters are listed in the table below image text in transcribed

a) Draw the network diagram. What is the expected completion time (state it explicitly)? What is the variance of project completion time? b) The deadline is 23 weeks. What is the probability of completing it on time? What is the probability of the project missing the deadline? c) What is the probability of finishing in 18.5 weeks or less? d) As project manager, you will be paid a bonus if you finish the project in 21 weeks or less. What is the probability of achieving the bonus? e) What is the probability of finishing between 21 and 23 weeks? f) What is the timeline that would achieve a 50% probability of finishing? What is the timeline that would achieve an 80% probability of finishing?

\begin{tabular}{|c|c|c|c|c|} \hline \multirow{2}{*}{ Activity } & \multicolumn{4}{|c|}{ Time estimate weeks } \\ \cline { 2 - 5 } & Optimistic & Most Likely & Pessimistic & ImmediatePredecessors \\ \hline A & 2 & 4 & 6 & \\ \hline B & 2 & 6 & 7 & \\ \hline C & 4 & 5 & 6 & A,B \\ \hline D & 1 & 2 & 3 & B \\ \hline E & 3 & 5 & 7 & C \\ \hline F & 1 & 3 & 4 & C,D \\ \hline G & 2 & 4 & 6 & E,F \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Systems Approach to Planning Scheduling and Controlling

Authors: Harold Kerzner

11th edition

1118022270, 978-1118415856, 111841585X, 978-1118022276

More Books

Students also viewed these General Management questions

Question

The front transperant part of the sclerosis known as.....?

Answered: 1 week ago

Question

What is the refractive index of the cornea....?

Answered: 1 week ago

Question

Common defects of the eye?

Answered: 1 week ago

Question

The eye is responsible for producing tears....?

Answered: 1 week ago

Question

Cause on the an increase in pressure with in the eye ?

Answered: 1 week ago