You have been contracted to undertake a project for a firm. The project parameters are listed in the table below. Task Length (weeks) Immediate Predecessors

You have been contracted to undertake a project for a firm. The project parameters are listed in the table below.

Task

Length

(weeks)

Immediate

Predecessors

Crash Cost per week Maximum weeks crashed
A 2 250 1
B 3 200 1
C 3 200 2
D 3 A, B 150 1
E 2 B, C 350 2
F 3 D 100 1
G 4 D, E 350 1
H 4 F, G 700 1
I 3 G 100 1

a) Draw a network diagram and determine the critical path for the project. What is the expected completion time (state it explicitly)? b) The client asks you to shorten the project by 3 weeks and will pay you a bonus of $1,200. Is this worthwhile? When you finish crashing 3 weeks from the project, which path or paths are critical?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals of Financial Management

Authors: Eugene F. Brigham, Joel F. Houston

Concise 6th Edition

978-0324664553

Students also viewed these General Management questions