You have been given the following information about the production of Tamarisk Co., and are asked to provide the factory manager with information for a
You have been given the following information about the production of Tamarisk Co., and are asked to provide the factory manager with information for a meeting with the vice-president of operations:
Standard Cost Card | |||
---|---|---|---|
Direct materials (6.00 kg at $3.20 per kilogram) | $19.20 | ||
Direct labour (0.70 hours at $4.50) | 3.15 | ||
Variable overhead (0.70 hours at $3.20 per hour) | 2.24 | ||
Fixed overhead (0.70 hours at $7.00 per hour) | 4.90 | ||
$29.49 |
The following is a production report for the most recent period of operations:
Variances | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Costs | Total | Price/ Rate | Spending/ | Quantity/ | Volume | |||||||||
Direct materials | $374,400 | $5,997 | F | $9,408 | U | |||||||||
Direct labour | 61,425 | 2,990 | U | 5,850 | U | |||||||||
Variable overhead | 43,680 | $1,020 | F | ? | ||||||||||
Fixed overhead | 95,550 | 410 | F | $14,000 | U |
How many units were produced during the period?
Number of units produced | enter the number of units produced |
How many kilograms of raw material were purchased and used during the period?
Raw materials purchased | enter the raw materials purchased in kilograms | kilograms |
What was the actual cost per kilogram of raw materials? (Round answer to 2 decimal places, e.g. 15.25.)
Actual cost per kilogram | $enter the actual cost per kilogram in dollars rounded to 2 decimal places /kg |
How many actual direct labour hours were worked during the period?
Actual direct labour hours | enter the actual direct labour hours | hours |
What was the actual rate paid per direct labour hour? (Round answer to 2 decimal places, e.g. 15.25.)
Actual rate | $enter the actual rate per hour in dollars rounded to 2 decimal places /hr |
What was the actual variable overhead cost incurred during the period?
Actual variable overhead | $enter the actual variable overhead in dollars |
What is the total fixed overhead cost in the company’s master budget?
Budgeted fixed cost | $enter the budgeted fixed cost in dollars |
What were the master budget hours for fixed overhead?
Master budget hours | enter a number of master budget hours | hours |
Step by Step Solution
3.53 Rating (170 Votes )
There are 3 Steps involved in it
Step: 1
Actual variable overhead 46820 Working i Standard variable overhead ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started