You have been hired to design User Interface for a Web Site that has five web pages. Each web page is scheduled to take one
You have been hired to design User Interface for a Web Site that has five web pages. Each web page is scheduled to take one day to complete at a cost of $500 per web page. At the end of day 2, you have spent $1100 and 1.5 pages are complete.
How is the project doing in terms of schedule and budget? Calculate SPI and CPI explain the solution.