You have been selected as the PM for a financial system development for a large organization which costs $5m and takes 2 years. After developing
You have been selected as the PM for a financial system development for a large organization which costs $5m and takes 2 years. After developing the PMP, youve identified a list of risks of different nature in terms of impact and probability.
a. Briefly describe the 4 different risk response strategies .
b. Now, identify 4 risks in this project with different level (low, medium, high) of impact and probability. For each of the 4 risks, apply one of the response strategies from (a) and justify your response by the impact and probability pair.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started