You have collected the following data based on three months of your project s performance. Complete the table. Calculate cumulative CPI ( CPIC ) .

You have collected the following data based on three months of your projects performance.
Complete the table. Calculate cumulative CPI (CPIC). How is the project performing after these
three months? Is the trend positive or negative?
EV EV C AC AC C CPI CPI C
January $30,000 $35,000
February $95,000 $100,000
March $125,500 $138,000
Overall, the project is performing below required levels (assuming CPI should equal 1.0 or
higher). However, the original poor value is trending moderately better (moving from 0.86
to 0.92 over three months). Trend is positive but the CPI is still under-performing

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals Of Project Management

Authors: Joseph Heagney

5th Edition

0814437362, 978-0814437360

More Books

Students also viewed these General Management questions

Question

=+ Do you see any potential problems with the analysis?

Answered: 1 week ago

Question

Describe five organizational development techniques.

Answered: 1 week ago

Question

Explain the two dimensions of an organizations culture.

Answered: 1 week ago

Question

State why people resist change and how to overcome resistance.

Answered: 1 week ago