You have four project seeking approval. Each costs $1,000. Which three do you choose to fund if your capital budget is $3,000? Project A B
You have four project seeking approval. Each costs $1,000. Which three do you choose to fund if your capital budget is $3,000?
Project A B C D
NPV $250 $150 $175 $200
Discount Rate 13% 7% 7% 10%
Project Life (years) 12 3 5 7
ABC |
ABD |
ACD |
BCD |