You have just begun working on a new project. During project initiation, your team came up with the following tasks, precedence relationships between tasks, and
You have just begun working on a new project. During project initiation, your team came up with the following tasks, precedence relationships between tasks, and expected duration of tasks for current resource allocations (in days). You also asked your team how to analyze whether it is possible to reduce the duration of any task, and how much such a reduction (= crashing) would cost. The Table below contains an overview of the data provided by your team.
\fTeam Data Task Predecessor Duration Crash Cost / Day Max. Crash (Days) A - 4 7000 2 B A 5 15000 1 C A 6 1000 2 D B 7 5000 3 E B 8 - 0 F C 6 500 2 G D 3 1000 1 H E.F 3 1500 1: I G 7 6000 2 J H 9 2500 4 K 1,J 6 10000 3 \fWork-Breakdown-Structure and Task Duration Estimates with Generic Resources Task Predecessor Duration (days) # of Resources 2 5 A 4 3 B A 2 C A B 2 6 D 4 U E B 4 C 4 F D 4 G 6 W H E.F N G,H 2 -Work-Breakdown-Structure and Task Duration Estimates with Specific Resources Task Predecessor Duration (days) Resource A N Kyle B A 4 Kathy C A 3 Kathy D B 2 Erin E B 5 Erin F C 4 Kathy G D 4 Sam H E.F 6 Erin - G,H 2 SamStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started