Answered step by step
Verified Expert Solution
Question
1 Approved Answer
You have just received the latest status updates from the team. Based on the progress to date, system testing is projected to take three weeks
You have just received the latest status updates from the team. Based on the progress to date, system testing is projected to take three weeks longer than planned. If this happens, user acceptance testing will have to start three weeks late, and the project will not complete on the planned finish date. The customer scheduled the user acceptance testing participants weeks in advance. What is the best course of action?
Explain to the test team that the system test must end on the scheduled date, and they are accountable for the accuracy of the testing results. A
B
Meet with the test team to determine the cause of the delay. If you determine that there are not enough testers to complete all of the scenarios in the time allotted, work with the sponsor to secure additional testers to complete the system test as planned. B
Submit the change request to the and, if it's approved, baseline the schedule again.
Escalate the issue of the system test delay to the sponsor and let them decide what action to take. D
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started