You have reached the end of Release One of the XYZ Business Workflow project, and your team has faced some challenges during the development process.
You have reached the end of Release One of the XYZ Business Workflow project, and your team has faced some challenges during the development process.
One software tester and one developer from your team resigned. You found replacements for both of them, but the new developer had to be trained by one of your other team members. This affected the team's productivity.
Also, during one of your status meetings with the client stakeholders, their product owner requested a change in a feature that was almost complete. They were also very resistant to give any additional time for the first release. As a result, you had to add extra hours to your development time.
To accommodate these changes, your team worked extra hours and even some weekends to complete the project. Finally, you managed to deliver the first release according to schedule.
The release goes fairly smoothly, but after a few days, the customer reports that their users are facing some issues with the software. They also have a list of changes and two new features they would like to see in the software before your final rollout in Release Two.
- Based on your experience with Release One, provide some recommendations for managing the second release of the XYZ Business Workflow software, including the methodology, change management, and quality control strategies.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started