You have recently joined as the project manager of ABC Company. Please refer to the Excel file to see the project information. a) Complete status

You have recently joined as the project manager of ABC Company. Please refer to the Excel file to see the project information.

  1. a) Complete status reports for periods 1 - 6.
Status Report: Ending Period 1
Task % Complete EV AC PV CV SV
A 25% 50
Cumulative Totals 50
Status Report: Ending Period 2
Task % Complete EV AC PV CV SV
A 50% 100
Cumulative Totals
Status Report: Ending Period 3
Task % Complete EV AC PV CV SV
A 100% 200
B 0% 0
C 0% 0
Cumulative Totals
Status Report: Ending Period 4
Task % Complete EV AC PV CV SV
A 100% 200
B 60% 100
C 50% 200
Cumulative Totals
Status Report: Ending Period 5
Task % Complete EV AC PV CV SV
A 100% 200
B 100% 200
C 100% 400
Cumulative Totals
Status Report: Ending Period 6
Task % Complete EV AC PV CV SV
A 100% 200
B 100% 200
C 100% 400
D 75% 100
Cumulative Totals

b) Complete the below performance indexes Summary Table

Period

EV

AC

PV

SPI

CPI

% Completion

1

2

3

4

5

6

c) Calculate the EAC, VAC, ETC, TCPI just for period 6. Assume CPI and SPI influence the remaining work.

d) Draw CPI and SPI graph; how this graph can help you to understand the project situation.

e) Based on your data, what is the project status at the end of period 6?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials Of Enterprise Risk Management

Authors: Rick Nason, Leslie Fleming

1st Edition

1947098365, 978-1947098367

More Books

Students also viewed these General Management questions

Question

Find an expansion of \(f(x)=\frac{1}{x+2}\) about \(x=1\).

Answered: 1 week ago

Question

15.2 Explain the costs associated with employee turnover.

Answered: 1 week ago