Question
You have started to identify the human resources and assign them to the activities. First, you assigned resources to the first seven activities as shown
You have started to identify the human resources and assign them to the activities. First, you assigned resources to the first seven activities as shown in the Table 2.
Table 2 Human resources assigned to the activities Activity Resources
A. Conduct competitive analysis PM1, PM2
B. Conduct tech capabilities assessment PM2, PM4
C. Develop focus group data PM3
D. Conduct telephone surveys PM4, MKT1
E. Identify relevant specification improvements PM2, PM3, MKT1
F. Interface with Marketing staff PM3, PM4, MKT1, MKT2
G. Develop engineering specifications PM2, ENG1, ENG2, PM3
Work on Remodeling_v2.mpp for this question
. Enter all the resources in the Resource Sheet in MS Project.
All of the human resources work full-time in the activities.
You wont write their standard rates (wage/hour). Assign all the resources to their activities
. Show the baseline on your Gantt chart.
Identify all the resource overallocation problems. Take a screenshot of WBS and Gantt Chart. This screenshot must show the first row Indicators. Paste this screenshot on your Word document
. Solve the overallocation problem in Activities A and B by removing PM2 from A. Conduct competitive analysis, and add PM3 in this activity.
For the Activities D and E, check the overallocation problem in Resource Graph for MKT1. Take a screenshot, and paste it on your Word document
. Level the resources for D and E. Your resource-leveling options must be as shown in Figure 1
Level the resources for D and E. Your resource-leveling options must be as shown in Figure 1.
For the new overallocation problem after you level the resources, apply Respect Links.
For F. Interface with Marketing staff and G. Develop engineering specifications, identify the source of the overallocation problem. Remove the human resource from Activity F to solve
the problem. Save Remodeling_v2.mpp, and submit it.
What other information is required to answer the question? , this is an inappropriate comment at least tell me what additional information is needed. So that I can Include
Figure 1 - Resource Leveling Options Resource Leveling Leveling calculations Automatic Manual Look for overallocations on a Day by Day basis clear leveling values before leveling Leveling range for 'Assignme' Level entire project Level From: Thu 10/29/20 To: Tue 1/5/21 Resolving overallocations Leveling order: Standard Level only within available slack Leveling can adjust individual assignments on a task Leveling can create splits in remaining work Level resources with the proposed booking type level manually scheduled tasks Help Clear Leveling. Level All OK Cancel Figure 1 - Resource Leveling Options Resource Leveling Leveling calculations Automatic Manual Look for overallocations on a Day by Day basis clear leveling values before leveling Leveling range for 'Assignme' Level entire project Level From: Thu 10/29/20 To: Tue 1/5/21 Resolving overallocations Leveling order: Standard Level only within available slack Leveling can adjust individual assignments on a task Leveling can create splits in remaining work Level resources with the proposed booking type level manually scheduled tasks Help Clear Leveling. Level All OK CancelStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started