You may need to use the appropriate technology to answer this question. completion date requested by the owner. The Mueller project manager prepared the following
You may need to use the appropriate technology to answer this question. completion date requested by the owner. The Mueller project manager prepared the following project network.
i
Estimates of the optimistic, most probable, and pessimistic times in weeks for the activities are as follows.
tableActivityOptimistic,Most Probable,PessimisticABCDEFGHa Find the critical path. Enter your answers as a commaseparated list.
b What is the expected project completion time in weeks
weeks
c Based only on the critical path, what is the estimated probability the project can be completed in weeks as requested by the owner? Round your answer to four decimal places.
d Based only on the critical path, what is the estimated probability the building project could run more than months late? Use weeks for this calculation. Round your answer to four decimal
places.
e What should the construction company tell the owner? Enter your freeform answer using as many characters as necessary.
This answer has not been graded yet.
Need Help?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started