You may need to use the appropriate technology to answer this question. Blue Lagoon is a contractor that installs residential swimming pools, projects that consist

You may need to use the appropriate technology to answer this question. Blue Lagoon is a contractor that installs residential swimming pools, projects that consist of nine major activities. The activities, their immediate predecessors, and the activity time estimates (in days) are shown.

Activity Immediate Predecessor Optimistic Most Probable Pessimistic
A 3 5 6
B 2 4 6
C A,B 4 5 6
D A,B 8 10 11
E B 2 4 6
F C 1 2 3
G D 4 9 11
H D, F 5 7 9
I E,G,H 3 4 5

(a) What are the critical activities? (Enter your answers as a comma-separated list.) (b) What is the expected time (in days) to complete the project? (Round your answer to two decimal places.) (c)Based only on the critical path, what is the estimated probability that the project can be completed in 27 or fewer days? (Round your answer to four decimal places.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions